Renovating in Spain is governed by different rules than in northern Europe. What would be a simple notification back home can require a full building permit here, and vice versa. This is what applies on the Costa Blanca.

Cosmetic work inside, such as painting, new surface finishes or repainting a facade in the same colour, normally needs no permit at all. The same goes for simple renovations that do not touch structure, installations or layout.

A building licence (licencia de obra) is required when you: change the layout, touch load-bearing walls, replace all installations, alter the facade's appearance, extend, or change how a space is used. Pools and major terrace changes are also covered.

A terrace renovation like this one changes the facade's use, and therefore needs a licence.
A terrace renovation like this one changes the facade's use, and therefore needs a licence.

Work that does not need a full licence may still require a declaración responsable: a written declaration that the work complies with current rules. It is easy to miss, and the municipality can stop work without it.

Licence times vary by municipality. Expect four to twelve weeks for smaller projects, longer when structure or facade is involved. Altea, Benidorm and Calpe each work at their own pace, and a local team knows what to expect where.

Our rule is simple: before the first hammer swings, we establish which permits apply, handle the applications with drawings and technical documentation, and do not start work until every document is in place. That way you avoid stopped work, retroactive fines, and problems when selling.

Questions about a specific project? Get in touch and we will review it and tell you which permit applies in your municipality.