To build a new home in Spain you need a major works license (licencia de obra mayor) from the town hall before any work starts. Your architect prepares the project, the town hall checks it against local planning rules, and you pay the license fee and the construction tax (ICIO). On the Costa Blanca approval often takes several months, and once the house is finished it needs a first occupation license before you can move in.
Why the license matters
The license confirms that your house complies with the municipal plan and with Spanish building regulations (the Código Técnico de la Edificación). Without it, the town hall can stop the work, impose fines and, in the worst case, order demolition. Banks, notaries and future buyers will also ask for it, so building without a license causes problems for as long as you own the property.
How to get a building license, step by step
It starts with the plot. Check what the municipal plan (PGOU) allows: how much you may build, the maximum height, the distances to the boundaries and any special protection. Your architect then draws up the project: a basic project (proyecto básico) for the application and an execution project (proyecto de ejecución) with the full technical detail, which is stamped (visado) by the professional college.
The application is submitted to the town hall together with the project and the appointment of the technical team that will supervise the work. You pay the license fee and the ICIO construction tax, both calculated on the budget of the project. The town hall's technicians may ask for corrections, and once the license is granted, work can start within the period it states.
Supervision during the build
In Spain the town hall does not inspect each stage of the build, as happens in some other countries. Instead the law requires a technical team, the dirección facultativa, made up of the architect and the technical architect (aparejador). They visit the site, check the work at each key stage and record it in the site book.
When the house is finished, they sign the certificate of completion (certificado final de obra). With that certificate you apply to the town hall for the first occupation license (licencia de primera ocupación, in many municipalities now handled as a declaración responsable), which confirms the home can be lived in.
Tips to avoid license delays
Most delays come from incomplete applications, so submit a complete, well-documented project the first time. Ask early how long your town hall is currently taking, as Altea, Benidorm and Calpe each work at their own pace, and plan the start of the build around it. Often the simplest option is to let your builder or project manager follow the application and deal with the town hall for you.
That work forms part of new construction, and the plot should be checked first: what to check before buying a building plot.
Frequently asked questions
-
Who applies for the building license?
The license is issued in the owner's name, but the application is normally prepared and followed up by the architect, builder or project manager.
-
What is the first occupation license?
The approval that confirms a finished home meets its license and can be lived in. You need it to contract water and electricity permanently and to sell or rent the house.